Electrics Tasks and duration

Item Description Duration (hrs:mins)
1 Mark up all connections on wire loom 4:00
2 Install loom through scuttle and transmission panel holes and install gromets. Install Fuseboxes 2:00
3 Install convoluted cable protection over entire loom 1:30
4 Rivet wireloom to chassis 6:40
5 Install positive feed from rear to front of car via transmission tunnel 0:20
6 Install battery box 1:30
7 Fit fuel inertia cut-off switch to chassis 0:15
8 Fit neoprene seal to rear chassis for fuel tank 0:15
9 Build megasquirt stimulator 0:40
10 Build and test megasquirt V3.0 11:30
11 Modify Megasquirt for EDIS8 ignition 2:00
12 Install front indicators 1:00
13 Make template, cut tub and fit side repeaters 4:00
14 Install rear lights 10:20
15 Install front headlights, make up pigtail looms 2:30
16 Install dash switches and make up pigtails looms, install to car loom plus design 20:30
17 Install immobiliser 1:00
18 Install Speedo sensor 0:20
19 Make neat behind dash wiring 1:30
20 Fix ECU to scuttle 0:30
21 Change connectors on loom for indicators 0:20
22 Change connector on loom for radiator fan switch 0:20
23 Install front indicators 3:00
24 Install coil packs and wire up HT leads 1:00
25 Design and looming of fuel injectors 5:00
26 Install additional fuse and relay box, re-routed P, PW, N3/4 wires 2:00
27 Install 6-way connector to engine loom 1:00
28 Wire engine sensors to ECU 5:00
29 Install speedo transducer 2:00
30    
     
  TOTAL (so far) 81:30

 

 

 